Quarry Landfill Update for January 20, 2023

Posted on January 20, 2023 at 3:30 PM by Joey Lamie

Sidewall Odor Mitigation System (SOMS) construction continued this week as crews pressed on through some inclement weather.  SCS Field Services was able to place clay fill and install an upper collector for Phase 1 of the SOMS project. In addition to making some progress on Phase 1, SCS Field Services worked on steps that could be undertaken for Phase 2 as they began digging and installing 140 feet of the lower collector. 

The bid process for the gas collection system expansion, which includes the drilling of 35 vertical gas wells, also closes this afternoon at 2 p.m. An update and additional details will be provided next week after the bid process closes and a contractor has been selected.