Posted on January 27, 2023 at 12:04 PM by Joey Lamie
Work continues on Phase 1 of the Sidewall Odor Mitigation System. This week, additional clay was moved on top of the higher horizontal collector. Wellheads connecting the horizontal collector pipes to the blower and flare were raised to above grade, and the installation of piping to the blower and flare was completed. Also, two feet of clay was backfilled up the wall to allow for concrete to be poured behind the rock fall protective barrier. Additional photos of the recent progress on the Sidewall Odor Mitigation System can be found on the landfill website at https://bristolvalandfill.org/progress.