Posted on March 31, 2023 at 12:40 PM by Joey Lamie
Installation of Phase 2 of the Sidewall Odor Mitigation System (SOMS) remains active. Installation of the lower horizontal collector is nearly complete and the liner crew is tying into it. The liner for the upper collector is approximately two-thirds complete. Drilling for the gas system expansion began on Wednesday. To date, three wells along the northern and northeastern walls have been installed and the crew is nearly complete with the fourth well. Any well not completed during the day will be covered by a vacuum box. Drilling activities related to the project will continue to occur between 7:00 a.m. – 6:00 p.m. each day.