Posted on April 14, 2023 at 12:00 PM by Joey Lamie
Work continued this week on Phase 2 of the Sidewall Odor Mitigation System (SOMS). Approximately 1,700 feet of the upper collector is now installed. Clay placement on the upper liner continues. Only one perimeter gas well remains to be drilled for the gas well expansion design. As a next step, the new perimeter wells will be hooked into the existing gas extraction system. Upon completion of the perimeter well system, the drilling crew will continue to drill for the non-perimeter wells.