Landfill Notifications and Information

BVSW logoCity of Bristol Virginia Landfill Information and Updates

View All Posts

May 05

Quarry Landfill Update for May 5, 2023.

Posted on May 5, 2023 at 11:10 AM by Joey Lamie

Work continues on the Sidewall Odor Mitigation System (SOMS). The lower collector is being placed in the eastern area of the landfill where the 12-inch header was relocated. Clay is being placed on the upper collector area around the landfill. The perimeter wells have been connected to the gas extraction system, increasing the combusted landfill gas volume at the flare. Two of the dual-phase, non-perimeter extraction wells have been completed. As drilling work continues, any well not completed during the day will be covered by a vacuum box at the end of the day.