Landfill Notifications and Information

BVSW logoCity of Bristol Virginia Landfill Information and Updates

View All Posts

Sep 22

Quarry Landfill Update for September 22, 2023

Posted on September 22, 2023 at 11:55 AM by Joey Lamie

Crews installed 13 Blackhawk pumps in select vertical gas extraction wells to remove condensate and leachate from the wells this week.  The vertical gas extraction pipe in the quarry landfill, which leads to the temporary flare, was also upgraded from a 6-inch diameter to a 12-inch diameter pipe to allow for greater condensate management and to increase the gas flow to the temporary flare.

 Additional air monitoring report summaries have been added to BristolVaLandfill.org and can be found at this link.