Posted on November 4, 2021 at 8:22 PM by Rick Belcher
November 4, 2021 LANDFILL UPDATE This morning, Teddy Blevins with SCS Engineers, arrived on-site to begin prep work for the gas well connections. Equipment was brought to the site today with additional equipment expected to arrive on Friday, November 5, 2021. SCS anticipates it will begin welding pipe for this project on Saturday and connections of the wells will begin early next week. Per the contract, SCS has 40 days to have the project gas well connections “substantially complete” and 50 days to have the project complete from November 5, 2021. The City anticipates 3-4 wells will be connected to the landfill gas collection system at a time