Posted on November 15, 2021 at 9:54 AM by Joey Lamie
Work completed on Friday, November 12, included completing an air test on the installed 12” header gas line, installed two 8” valves, performed grading for installation of lateral pipes, installed 458 LF of 4” header and lateral piping, installed five 4” vacuum risers at the wells in the north end, and installed one 6”x4”x4” tee. Work completed on Saturday, November 13, included the installation of a 40’ road crossing, including header and lateral piping, installed one well pump and wellhead (GW64), and measured well depths and water levels at the four northern wells (GW32R, GW62, GW63, GW64).