Posted on November 22, 2021 at 9:05 AM by Joey Lamie
Work completed on Friday, November 19, included installation of 468 LF of 8” header pipe, 260 LF of 6” header pipe, two 4” valves, and two 8” valves. Also raised existing gas well GW56 10 vertical feet. Work completed on Saturday, November 20, included completion of the 8” and 6” header pipe installation and conducting an air test on the header line. Also measured depths and water levels in remaining new wells, located on the southern portion of the landfill.