Posted on December 2, 2021 at 2:09 PM by Joey Lamie
Work completed on December 1, 2021, included installation of 200 LF of 4” lateral piping and risers at wells, conducted air test on piping installed (passing results), installed wellheads, and connected eight new wells (GW68, GW51, GW52, GW54, GW57, GW66, GW58, and GW67).