Posted on December 4, 2021 at 7:11 PM by Joey Lamie
Work completed on Thursday, December 2, included moving a 4” valve to the low point at the south end to drain the header pipe line and assembling air line and force main parts.
Work completed on Friday, December 3, included the installation of 105 LF of 8” header piping, 172 LF of 4” lateral piping, 155 LF of 4” force main, and 155 LF of 2” air line. Performed a pressure test on the lateral piping at GW31r. Also installed 3 force main risers and 3 air line risers and a 40 LF road crossing.