Landfill Notifications and Information

BVSW logoCity of Bristol Virginia Landfill Information and Updates

View All Posts

Dec 10

Landfill Update for December 10, 2021.

Posted on December 10, 2021 at 4:34 PM by Joey Lamie

Work completed on Thursday, December 9, included the installation of air and forcemain piping to well GW55 (approx. 12’) and 469 LF each of air line and forcemain line to stub up at wells GW54, GW67, GW51, GW52, and GW 68.  Also, 8” header piping was installed to wells GW54 (~172 LF), continued on to GW47, then GW 67 (~90 LF); from tee near GW55 to GW68 (~112 LF), on to GW52 (~53 LF), and on to GW51 (~30 LF).  Pumps in a few of the wells were tested to make sure they were operational. 

Work completed on Friday, December 10, included receiving the new sump to install north of HSC-1, and water pumps were installed in GW67 and GW55, including construction/assembling parts for pump connections.