Posted on December 5, 2022 at 8:15 AM by Joey Lamie
As of December 2, Connelly & Associates has completed seven (7) of the nine (9) borehole drillings in relation to the installation of the thermocouple system at the quarry landfill. The probes in each well have been set at 165 feet, 155 feet, 218 feet, 200 feet, 202 feet, 208 feet and 222 feet respectively. Significant progress has also been made on Well 8 with just a few feet left to complete the drilling on that well. The well casing pipe has been installed in the seven (7) completed boreholes and we anticipate the final two (2) boreholes will be completed with the installation of the temperature monitoring equipment well before the December 31 deadline.
On Tuesday, December 6, City Council is also scheduled to vote on the lone bid it received from SCS Field Services for the Sidewall Odor Mitigation System. The City will provide an update on the anticipated timeline and subsequent work schedule next week if the bid is accepted.