Quarry Landfill Update for January 6, 2023

Posted on January 6, 2023 at 3:34 PM by Joey Lamie

Sidewall Odor Mitigation System (SOMS) construction continued this week with good progress. SCS Field Services has been working on the wall preparation with concrete application scheduled to begin on Monday (1/9). Construction of this pilot (test) section of the wall is on schedule.

A graphic of the design for the Sidewall Odor Mitigation System can be found on the BristolVALandfill.org site under the Resources/FAQs section. 

The City is in the planning stages of hosting a second Open House to provide an update on the work at the Quarry Landfill and hopes to announce the date soon.